NOTE: Please check our Weekly Team Updates for all the changes that have occured since the beginning of the semester.
We encountered two main set backs as we entered the Fall of 2004. Primarily our intention of using the CHIPCON RF development kit from the previous design team was dashed and our original advisor [Dr. Lee] had to leave the university because of family issues.
With the departure of our original advisor, went our CHIPCON RF development kit, effectively placing our teams progress on hold. Losing the kit meant that we had lost all the progress made by both ourselves and the previous design team. We would now have to concieve of a new way to solve our assignment. Our solution was to purchase an RF development kit from a company called Radiotronix. All our original intentions and goals still remain true, only now the pressure has increased as we face the same amount of work, with only half the time. Please visit our Weekly Team Updates for more details.