Progress Updates


+ 2005.11.30

+ 2005.11.09

+ 2005.10.26

+ 2005.10.19

+ 2005.10.12

+ 2005.10.05
  1. Work Completed
    1. Project Statement finalized. Turned in and posted on the website
    2. Website redesigned by Chris Johnson
    3. Received 2 computers for our lab bench, still waiting for a 3rd
    4. Reviewed SDS
  2. Future Work
    1. Start Project Specification and have it finalized by 10/12/04
    2. Meet with Dan from ASML to setup software on our computers
    3. Once software is setup, begin to learn how to use it
    4. Email Veiraf with questions concerning the project
    5. Get in touch with Paul and find out about a 3rd computer
    6. Keep reviewing SDS
  3. Status of Project
    1. Software still needs to be installed, waiting on a confirmation date from Dan
    2. Need more insight from Viraf, what ASML expects as an end product

+ 2005.9.28
  1. Met with John Chandy
    1. Discussed status of Project Statement; Agreed to have it completed by 2005.10.5
    2. Verified completion of NDA's
    3. ---
  2. Week in Review
    1. Completed NDA's
    2. Received 'Green Book' (Software Design Specification) and 'Yellow Book' (User Manual) of the Twinscan system via email
    3. Conference Call w/ David Burry of ASML
      1. Discussed preliminary project specifications
      2. Set a tentative date for software installation on our hardware on 2005.10.4